Published: Fri, 6 Nov 2009
Description: (NECN/AP: Boston, Mass.) - The nation's first offshore wind farm faces more delay after a top Massachusetts historic preservation officer said Thursday that two Indian tribes' claim to Nantucket Sound needed more study. The d...
Automatically Generated Transcript (may not be 100% accurate)
" spent more than seven years since it was first proposed and now there is another delay in the cape wind project. The planned wind farm off the Massachusetts coast is facing a total from state historic officials and Indian tribes. The officials are calling for a study into claims from the tribes who say the proposed 130 wind towers would block their view of the sunrise and interfere with tribal rituals earlier this year federal environmental officials gave their final approval to the project."